AERB Clears RAPP-8 for First Approach to Criticality: India's Fourth Indigenous 700 MWe PHWR
On 19 November 2026, the Atomic Energy Regulatory Board allowed the First Approach to Criticality of Unit 8 of the Rajasthan Atomic Power Project at Rawatbhata, the fourth reactor of India's indigenous 700 MWe PHWR series.
Why in the news?
On 19 November 2026, the Atomic Energy Regulatory Board (AERB) gave permission for the First Approach to Criticality (FAC) of Unit 8 of the Rajasthan Atomic Power Project (RAPP-8) at Rawatbhata in Chittorgarh district, Rajasthan. The Press Information Bureau published the decision on 20 November 2026. RAPP-8 is a 700 MWe Pressurised Heavy Water Reactor (PHWR) built by the Nuclear Power Corporation of India Limited (NPCIL). It is the fourth reactor of India's indigenous 700 MWe PHWR design to reach this stage.
Background
- What criticality means: A reactor is "critical" when the fission chain reaction becomes self-sustaining, so each fission event on average causes exactly one more. The first approach to criticality is the first time a newly built reactor is brought to this state, at very low power and under close control.
- Where RAPP-8 stands: AERB had earlier allowed initial fuel loading. Fuel loading began on 19 September 2026 (World Nuclear News; NPCIL announced it on 20 September). FAC is the next step. After criticality, the unit goes through low-power physics tests, then grid synchronisation and a step-by-step rise in power. Each stage needs a separate AERB clearance.
- How AERB decided: According to PIB, the permission followed a safety review of the reactor's design, construction, commissioning test results and operational readiness. The review included assessments by AERB's safety review committees, regulatory inspections and deliberation by the Board. AERB's resident site observers will keep watching the unit.
- The site: Rawatbhata is one of India's oldest nuclear sites. PIB notes it now has eight nuclear power units.
For an earlier look at nuclear plans in the eastern states, see Bihar energy MoUs on nuclear and pumped storage.
Key facts
| Item | Detail |
|---|---|
| Reactor | RAPP Unit 8, Rawatbhata, Chittorgarh (Rajasthan) |
| Type and size | Pressurised Heavy Water Reactor, 700 MWe, indigenous design |
| Operator | NPCIL (under the Department of Atomic Energy) |
| Regulator's decision | FAC permission granted on 19 November 2026 (PIB, 20 Nov 2026) |
| Fuel loading | Began 19 September 2026, after AERB permission |
| Position in series | Fourth 700 MWe PHWR, after KAPP-3, KAPP-4 and RAPP-7 |
| Commercial operation | NPCIL targets the current financial year, 2026-27 (Business Standard) |
Status of India's 700 MWe PHWRs (verified)
| Unit | Status |
|---|---|
| Kakrapar-3 (Gujarat) | First criticality July 2020; commercial operation July 2023 (WNN) |
| Kakrapar-4 (Gujarat) | First criticality December 2023; commercial operation March 2024 (WNN) |
| RAPP-7 (Rajasthan) | First criticality September 2024; grid connection March 2025; commercial operation in 2025; first reached full 700 MW on 10 February 2026 (WNN) |
| RAPP-8 (Rajasthan) | FAC cleared on 19 November 2026 |
| Other units | Sanctioned in fleet mode at Kaiga (Karnataka), Gorakhpur (Haryana), Chutka (Madhya Pradesh) and Mahi Banswara (Rajasthan) (WNN) |
Business Standard reports that RAPP-8 is the fourth of 16 indigenous 700 MWe PHWRs. NPCIL runs 24 reactors with 8.78 GWe of capacity (Business Standard; the 8.78 GW figure also appears in the PIB factsheet of April 2026).
Significance
- Domestic technology: The 700 MWe PHWR is the largest reactor India has designed on its own. Each new unit that runs smoothly makes the design more mature and builds confidence for the units now under construction.
- First stage of the three-stage programme: PHWRs burn natural uranium. Their spent fuel is the source of plutonium for fast breeder reactors, the second stage. The 500 MWe Prototype Fast Breeder Reactor (PFBR) at Kalpakkam reached first criticality on 6 April 2026 (DAE). More PHWRs therefore support the whole chain that is meant to lead to thorium use.
- Clean, steady power: Nuclear plants give round-the-clock low-carbon electricity. This balances solar and wind, which vary with the weather. PIB puts nuclear's share of electricity generation at about 3% in 2024-25.
- Credible regulation: A clear, staged clearance process, with every step reviewed separately, builds public trust. That trust matters as the sector opens to new operators.
Challenges
- Speed of build-out: India has about 8.78 GW today and wants 100 GW by 2047. That needs a much faster pace of construction than the past.
- Long timelines: RAPP-7 took about six months from first criticality to grid connection and almost a year more to reach full power. Commissioning cannot be rushed.
- Fuel supply: Domestic uranium reserves are limited (PIB factsheet), so imports and fuel-cycle capacity matter.
- Regulatory capacity: More reactors, new SMR designs and private operators will add to AERB's workload. It will need more skilled staff.
- Public acceptance and liability: Land, local consent, waste handling and liability rules remain sensitive. These questions shaped the debate on the SHANTI Act.
Way forward
- Use the fleet-mode approach fully: standard design, bulk orders and repeat suppliers to cut cost and time.
- Strengthen AERB's people and tools now that the SHANTI Act gives it statutory status.
- Grow fuel supply through domestic exploration and long-term import contracts. Also scale up reprocessing to feed the fast breeder stage.
- Be open with the public about safety reviews, emergency plans and waste management.
- Develop SMRs under the Nuclear Energy Mission alongside the large PHWR programme.
Facts for Prelims
- AERB: Set up on 15 November 1983 by the President under the Atomic Energy Act, 1962; headquarters at Niyamak Bhavan, Anushaktinagar, Mumbai (AERB website). The SHANTI Act, 2025 gives it statutory status (PIB).
- SHANTI Act, 2025: Sustainable Harnessing and Advancement of Nuclear Energy for Transforming India Act. Parliament passed it in December 2025 and the President gave assent (News On AIR, 22 Dec 2025). It replaces the Atomic Energy Act, 1962 and the Civil Liability for Nuclear Damage Act, 2010, and allows licensed private and joint-venture participation.
- Nuclear Energy Mission: Announced in the Union Budget 2025-26 (1 February 2025). It has Rs 20,000 crore for SMR research and aims for at least five indigenous SMRs working by 2033. The target is 100 GW of nuclear capacity by 2047.
- Three stages: (1) PHWRs on natural uranium; (2) fast breeder reactors on plutonium, breeding U-233 from thorium; (3) thorium-based reactors using U-233.
- PFBR: 500 MWe, Kalpakkam (Tamil Nadu), built by BHAVINI and designed by IGCAR; first criticality on 6 April 2026.
- PHWR basics: Uses natural uranium as fuel and heavy water as both moderator and coolant.
Mains practice question
"The commissioning of indigenous 700 MWe PHWRs is central to India's three-stage nuclear programme and its 100 GW target for 2047." Discuss this statement and examine the regulatory and capacity challenges involved. (250 words)
FAQs
What has AERB approved for RAPP-8?
On 19 November 2026, AERB allowed the First Approach to Criticality, which means bringing the reactor to a self-sustaining chain reaction for the first time at low power.
Does this mean RAPP-8 is now supplying power?
No. Low-power physics tests, grid synchronisation and a gradual rise in power must come first, and each step needs AERB clearance. NPCIL aims for commercial operation during 2026-27.
Which other 700 MWe PHWRs are working?
Kakrapar-3 and Kakrapar-4 in Gujarat and RAPP-7 in Rajasthan are in commercial operation. More units are sanctioned in fleet mode at Kaiga, Gorakhpur, Chutka and Mahi Banswara.
How does the SHANTI Act affect AERB?
The Act gives AERB statutory status within the main nuclear law. Before this, AERB had been set up in 1983 by an executive order under the Atomic Energy Act, 1962.
Sources
- PIB: AERB approves First Approach to Criticality of RAPP Unit-8 (20 Nov 2026)
- PIB Factsheet: PFBR criticality and India's nuclear programme (7 Apr 2026)
- DAE: Prototype Fast Breeder Reactor at Kalpakkam attains first criticality
- PIB: Parliament passes the SHANTI Bill, 2025 (18 Dec 2025)
- News On AIR: President gives assent to SHANTI Bill (22 Dec 2025)
- AERB: About us
- Business Standard: RAPP-8 begins fuel loading (20 Sep 2026)
- Swarajya: AERB clears RAPP-8 for first approach to criticality
- World Nuclear News: Indian plants celebrate fuel loading milestones (21 Sep 2026)
- World Nuclear News: Rajasthan unit 7 reaches full power
- World Nuclear News: Indian budget launches Nuclear Energy Mission

Ankit Kumar is the founder and editor of Tathyo. He works with BPSC and UPSC aspirants at GS Hub, Patna. At Tathyo, he oversees fact-checking so every article is exam-relevant and based on official sources.
Read also
Chariot-1 Sovereign Foundation Models Launched under the IndiaAI Mission: An 11-Billion-Parameter LLM and Text-to-Speech in 10 Indian Languages
On 26 November 2026, the Chariot-1 language model and an Indian-language text-to-speech model, both pre-trained from scratch in India, were launched at Bharat Mandapam, New Delhi, under the IndiaAI Mission.
ICMR SAMPADA Survey: Two-Thirds of Indian Adolescents Deficient in Vitamin B12, Anaemia Lower Than Before
ICMR-NIN's SAMPADA survey (2023-25) finds vitamin B12 deficiency in 66.1% of adolescent boys and 65.4% of adolescent girls, while anaemia is lower than in previous national surveys. Key data, Anaemia Mukt Bharat and fortification context for UPSC.
GRSE Delivers ASW Shallow Water Craft 'Ashank' to the Indian Navy
On 23 November 2026, GRSE delivered the Anti-Submarine Warfare Shallow Water Craft Ashank (Yard 3036) to the Indian Navy at Visakhapatnam. The programme, features, indigenous content and UPSC relevance explained.